Western Campus Preventative Maintenance of Main Electrical Equipment

Agency: Cuyahoga Community College
State: Ohio
Type of Government: State & Local
Category:
  • J - Maintenance, Repair, and Rebuilding of Equipment
Posted: Apr 2, 2024
Due: Apr 25, 2024
Publication URL: To access bid details, please log in.
Issued Item Specifications Due Date Award Recipient/Bid Tabulation
4/2/24

REQUEST FOR PROPOSAL

Western Campus Preventative Maintenance of Main Electrical Equipment

"Project No 7086" - click to view

Western Campus

Parma, OH

4/25/24 @ 2:00pm

Attachment Preview

Western Campus
Preventative
Maintenance of Main
Electrical Equipment
Project Number: 7086
Cuyahoga Community College
Western Campus
11000 W. Pleasant Valley Rd.
Cleveland, Ohio 44130
REQUIREMENTS AND
SPECIFICATIONS FOR WORK SCOPE
Electrical Contracting
Bid DUE Date: April 25, 2024 by 2:00 p.m. EST
Sealed Hard Copy and must include One Electronic (jump drive) copy bids will be
received by:
Judi Cooper
Cuyahoga Community College District Office
700 Carnegie Avenue
Cleveland, Ohio 44115
Mandatory Pre-Bid meeting On-site: April 11, 2024 at 11:00 a.m. EST
Recreation Center entry at northwest corner of Main Building, Parking Lot #A off Letterman Dr.
RFI’s Deadline: April 16, 2024 by 12:00 p.m. EST
Prepared by:
Karpinski Engineering
3135 Euclid Avenue
Cleveland, Ohio 44115
Phone: (216) 391-3700
Contact: Dave Woytek, dwoytek@karpinskieng.com
Table of Contents
PROCUREMENT AND CONTRACTING REQUIREMENTS
Procurement and Contracting Requirements
Introductory Information
Table of Contents
Procurement Requirements
00 31 32..............Preventative Maintenance Program
00 41 13..............Bid Form
Contracting Requirements
00 62 46..............Contractor’s Personal Property Tax Affidavit
Appendix
Cuyahoga Community College — Contractors Safety Guide
Refer to contract drawing documents for equipment locations and one-line diagrams.
END OF DOCUMENT
Document 00 31 32 – Western Campus
Preventative Maintenance Program for Main Electrical Equipment
Equipment summary:
1. Base Bid Preventative Maintenance (PM) program includes medium voltage switchgear,
medium voltage primary switches and transformers / unit substations, secondary
switchboards, motor control centers, 480volt distribution panels 800amps and above,
208volt distribution panels 800amps and above, and associated distribution stepdown
transformers. Include ancillary devices, overcurrent protection devices, busbars,
conductors and grounding connections located within this equipment.
2. Alternate Bid Item #1 Preventative Maintenance (PM) program includes 480volt,
400amp and 600amp distribution panels, 208volt, 400amp and 600amp distribution
panels, and associated distribution stepdown transformers. Include ancillary devices,
overcurrent protection devices, busbars, conductors and grounding connections located
within this equipment.
3. Alternate Bid Item #2 Preventative Maintenance (PM) program includes Thermal
Imaging of Base Bid equipment.
4. Alternate Bid Item #3 Preventative Maintenance (PM) program includes Thermal
Imaging of Alternate Bid Item #1 equipment.
5. Specific equipment to be included in this PM program is indicated on the accompanying
drawings and one line diagram.
6. Equipment located in the Simulation Village buildings, Fire Center, Public Safety
Training Center (PSTC, formerly Crile Building), Advanced Automotive Technology
Center (AATC), Maintenance Garage, and the new STEM Center is EXCLUDED. Also
excluded are “Site Watch” central monitoring equipment, generators, transfer switches,
UPS’s, panels rated below 600amps (and associated stepdown transformers), and
standalone starters, VFD’s and disconnect switches.
General Requirements:
1. Contractor shall perform preventative maintenance as recommended by equipment
manufacturers and by industry recommended practices. Maintenance shall be performed
in compliance with manufacturer’s recommended specifications and test values. CCC
does not have original operating and maintenance manuals. Contractor shall contact
manufacturers to obtain the manuals for recommended PM guidelines. Should operating
and maintenance manuals not be available for all equipment, Contractor shall reference
the InterNational Electrical Testing Association’s (NETA) standards for testing electrical
equipment specific to this PM program, in particular the requirements and tables
referenced in the most current NETA Maintenance Testing Specifications (MTS), or the
guidelines in NFPA 70B (Recommended Practice for Electrical Equipment
Maintenance).
2. Contractor shall provide evidence of similar experience and relevant qualifications such
as being a NETA Accredited Company to perform testing and maintenance of the
equipment included in this PM program. Maintenance shall be performed only by
properly trained and qualified personnel. Provide a list of qualified personnel and
evidence of training to CCC prior to commencing work. A minimum of two personnel is
required while performing maintenance on equipment. Personnel shall demonstrate a
00 31 32
Page 1 of 10
complete understanding of the equipment, the required work scope, and electrical hazards
present.
3. All procedures and guidelines of CCC shall be adhered to, including required safety /
lockout tagout procedures and relevant construction / contractor procedures. If not all
contained in this RFP, CCC will provide copies of additional procedures and guidelines.
Contractor shall also follow their own internal safety procedures, work plans, and hazard
mitigations plans.
4. Contractor shall visit the site prior to bidding and shall become familiar with the existing
conditions. Bid shall include contingencies related to relevant existing conditions.
5. Contractor will be required to notify designated CCC representative upon arrival to site
and upon leaving the site each day.
6. Contractor shall make proper use of personal protective equipment (PPE), tools, shielding
and test equipment, as well as precautionary techniques required by OSHA and NFPA
70E (Standard for Electrical Safety in the Workplace).
7. Any new work shall be installed in accordance with the latest version of the National
Electrical Code.
8. Contractor shall provide temporary power and lighting to complete required testing
during power shutdowns. 120 volt power utilized shall be ground fault protected.
9. Contractor will be required to provide a schedule, sequence of PM, and coordinate all
shutdowns with CCC. It is CCC’s intention that required shutdowns be performed during
off hours, weekends, and during academic breaks (such as after spring semester is
complete and before summer semester begins). Contractor shall make all attempts to limit
the duration of outages.
10. CCC will identify any critical equipment or areas that cannot be without power -
coordinate related temporary power requirements with CCC.
11. Contractor shall alert CCC representative immediately should any issues arise during
maintenance procedures.
12. Contractor shall include standard corrective actions and expected parts required by
routine maintenance in bid. Should replacement of devices or unanticipated components
be required, coordinate with and obtain approval from CCC prior to procurement.
13. Contractor shall summarize maintenance procedures and findings in a written report in a
standardized and consistent format. At a minimum, report shall include as-found
conditions with photographs, observations, test values obtained compared to
recommended values, deficiencies, corrective actions taken, further recommendations,
settings, and as-left conditions with photographs. If bid alternate is accepted, include
thermal imaging as summarized below.
14. Contractor shall provide maintenance tags with current dates and when the next
inspection is required.
Preventive maintenance checklist:
1. Alternate Bid Item #2 and #3 per above – Thermal Imaging:
o Before beginning the PM process, conduct Thermal Imaging Surveys to detect
potential:
Excess heat in electrical components
Loose connections
00 31 32
Page 2 of 10
Corroded elements
Short circuits
Overloaded circuits
Busbar-joint wear
o Performing the thermal imaging prior to beginning PM may allow a better
understanding of equipment needs, of potential repairs required during PM, and to
expedite the procurement process for replacement parts.
o Prepare reports for Owner’s records. Reports should include:
Documentation of type and manufacturer of thermal imaging equipment
used.
Description of equipment tested.
Areas inspected and any discrepancies or inaccessible components.
Images of thermal scans.
Load conditions at time of inspection (maximum loading is ideal).
Temperature difference between reference area and area of concern.
Potential cause of temperature difference.
Corrective actions taken.
Recommended courses of actions to addresses potential issues in the
future.
o Repeat imaging on areas after corrective actions are complete to document repairs
were successful.
2. Perform the following common maintenance on all equipment as applicable:
o Inspect electrical rooms and working space conditions. Note any evidence of
water, moisture, excessive temperatures, working clearance violations, etc.
o Check for any visible signs of damage, wear, or overheating on equipment
exterior enclosures as well as inside equipment. Inspect mounting and alignment
of equipment. Check for signs of insects or rodents within enclosures.
o In general, clean, inspect, tighten, lubricate and exercise equipment.
o Replace all filters, confirm all vents are clear.
o Inspect equipment busbars. Check supports, alignment, straight runs, joints,
directional change pieces, panel flanges and grounding connections / continuity.
o Inspect electrical cables and wiring (5kV and 600V). Check for any signs of wear,
damage, corrosion, or insulation deterioration. Verify cable connections are tight
and properly secured. Check cable routing to ensure it complies with safety
standards. No additional testing shall be performed on 5kV cables.
o Wipe down busbars, insulators and conductors with a dry lint-free cloth.
o Inspect grounding / bonding systems and connections for corrosion or damage.
Measure ground resistance to ensure it falls within acceptable limits. Verify
proper bonding between electrical equipment and grounding systems.
o As applicable, perform electrical testing of equipment components as
recommended by manufacturers as part of the PM process. Tests may include, but
are not limited to:
Testing of bolted electrical connections using calibrated torque wrench
method.
Insulation resistance tests.
00 31 32
Page 3 of 10
This is the opportunity summary page. You are currently viewing an overview of this opportunity and a preview of the attached documentation. For more information, please visit the Publication URL Web page.
Daily notification on new contract opportunities

With GovernmentContracts, you can:

  • Find more opportunities and win more business
  • Receive daily alerts for all new bid opportunities
  • Get contract opportunities matched to your business
ONE WEEK FREE TRIAL

See also

Bid Number Status Project Name Department Buyer Type Goal Type Goal % Date

City of Cincinnati

Bid Due: 12/12/2024

OWP - Athens 12 December 22, 2023 | ODNR Project Name Athens 12

State of Ohio - Department of Natural Resources

Bid Due: 1/25/2025

Bid Number Status Project Name Department Buyer Type Goal Type Goal % Date

City of Cincinnati

Bid Due: 5/31/2024

Follow BELT,VEHICULAR SAFE Active Contract Opportunity Notice ID SPE7LX24RX030 Related Notice CL23216001 Department/Ind.

Federal Agency

Bid Due: 11/04/2024

* Disclaimer: Information regarding bids, requests for proposals (RFPs), or requests for qualifications (RFQs) is provided on this website only as a convenience and does not constitute official public notice. Persons wishing to respond to or inquire about bids, RFPs, or RFQs should contact the appropriate government department.