Addendum #2
to
Spotsylvania County
IFB 24-33-SD
ROUTE 1 SEWER REPLACEMENT
February 20, 2024
Addendum #2 to Invitation for Bid (IFB) No. 24-33-SD is issued in accordance with the IFB Terms
& Conditions and is intended to provide additional information and clarification to Respondents.
Addendum #2 consists of two (2) items which are listed below, attached hereto and made a part
hereof to IFB No. 24-33-SD.
ITEM 1 – CHANGES TO IFB
1. Technical Specifications
01 29 01 Measurement and Payment
REPLACE entire Specification Section 01 29 01 Measurement and Payment, with the
revised Specification Section 01 29 01 Measurement and Payment – Revised, attached
hereto as Attachment A. Modified sections are underlined.
2. SECTION B – Bid Forms
REPLACE SECTION B – Bid Forms with the revised Bid Forms attached hereto as
Attachment B.
ITEM 2 – Q&A
1. This RFI concerns the specification for steel casing pipe; the specification calls for
“seamless” casing pipe. Is rolled and welded steel acceptable?
Addendum 2
IFB No. 24-33-SD
Page 1 of 2
ANSWER: Yes, rolled and welded steel will be acceptable as long as it meets the
requirements.
2. Bid Item No. Z (Note: now Item No. AA) on the Section B Bid Form calls for 1,075/EA
of Wetland Plantings. Where are these identified on the Drawings? Is there a
specification as to what specific plantings should be bid?
ANSWER: See attachment F of the IFB.
3. Since there is no Geotechnical soil reports available, are prospective bidders able to do
dig test pits along the proposed pipeline route?
ANSWER: The proposed bidders may preform dig testing as long as they are within the
County easement(s). The proposed bidders shall conform to all State and County
requirements regarding access, land disturbance and erosion and sediment controls.
4. Would Tindall’s T-Series manholes be accepted as an alternate to a standard round
manhole?
ANSWER: The County will accept Tindall’s T-Series manholes as an alternate as long as
they meet the County standards. Please submit documentation that they meet the
standards.
5. Please note that Contract Item No. “U” - 50” Steel casing appears to represent the supply
and installation for both a 50” Steel Casing that is installed by Jack & Bore, as well as,
50” Casings that is installed by open cut at several stream crossings.
Please be advised the installation of that casing by Jack & Bore is significantly different
than installation by open cut with substantial costs variations.
Also, the installation by open cut is a “Self Performed” item, while the installation by
Jack & Bore is performed by a specialty Sub-Contractor.
Considering the above, we are requesting that separate contract pay items be provided for
the 50” Casing by Jack and Bore and 50” Casings at stream crossings.
ANSWER: The Bid form has been updated. See attached.
ATTACHMENTS:
Attachment A – Revised Specification Section 01 29 01 – Measurement and Payment
Attachment B – Section B – Bid Forms - revised
Respondents shall acknowledge receipt of this Addendum with IFB submission.
Sylvia Dyson
Sr. Procurement Officer
February 20, 2024
Date
Addendum 2
IFB No. 24-33-SD
Page 2 of 2
ATTACHMENT A to Addendum 2
IFB #24-33-SD
SECTION 01 29 01 - REVISED
MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.01 GENERAL
A. The Contractor shall receive and accept the compensation provided in the Bid and the
Contract as full payment for furnishing all labor, materials, tools, equipment and services
for performing all operations necessary to complete the Work under the Contract, and
also in full payment for all loss or damages arising from the nature of the Work, or from
any discrepancy between the actual quantities of Work and the quantities herein estimated
by the Engineer, or from action of the elements or from any unforeseen difficulties which
may be encountered during the prosecution of the Work until the final acceptance by the
Owner.
B. The lump sum price stated in the Bid includes all costs and expenses for taxes, labor,
equipment, materials, commissions, transportation, patent fees and royalties, labor for
handling materials during inspection, together with any and all other costs and expenses
for performing and completing the Work as shown on the Contract Drawings and as spec-
ified herein. The basis of progress payments of said lump shall be broken down and de-
tailed in the Schedule of Values in accordance with the description of the representative
items in this section.
C. The Contractor’s attention is called to the fact that the quotations for the various items of
the work are intended to establish a total price for completing the Work in its entirety.
Should the Contractor feel that the cost for any item of work has not been defined by a
Bid Form, he must bring this to the attention of the Owner during the bid question period.
If the Owner finds the request to be valid, it may be added to the bid form. If the request
is found to be incidental to the project, the contractor shall include the cost for that work
in some other applicable bid item, so that his proposal for the work reflects his total price
for completing the work in its entirely.
D. Items listed as “CONTINGENT ITEM” in the Bid Form are to be used and will be paid
for only at the written direction and authorization of the Owner. Payment under this
section will be made for materials furnished and placed in addition to those shown or
beyond the limits indicated or reasonably inferred by the Contract Documents. Measure-
ment and payment will be in accordance with the Schedule of Values and will include,
but not necessarily be limited to, furnishing, hauling, placing and installing of materials
and the furnishing of such manpower and equipment as required to accomplish the Work
as directed in writing by the Owner.
E. Changes and Modifications in the Work by the Owner
Route 1 Sewer Replacement
Measurement and Payment
Section No. 01 29 01-1
ATTACHMENT A to Addendum 2
IFB #24-33-SD
1. The Owner reserves the right to change the alignment, grade, form, length, dimen-
sions, or material of the Work under the Contract, whenever conditions or obstruc-
tions are met that render the changes desirable or necessary. All such alterations
shall be paid for under the total lump sum bid or at a unit price bid for these items
of Work, except as follows:
a. In the cases where such alterations reduce the total Contract amount, a
Change Order shall be executed to reduce the total Contract amount, and the
Contractor shall have no claim on this account for damages or for anticipated
profits on the Work that may be dispensed with.
b. In the cases where such alterations increase the total Contract amount, a
Change Order shall be executed to increase the total Contract amount.
c. Any additions or subtractions to the contract prices shall be proposed by the
Contractor and then reviewed and approved by the Owner.
d. In case the quantity of work in individual unit price items of work increases
or decreases greater than 20 percent of the bid quantity, unit prices may be
renegotiated.
F. Owner May Increase or Decrease Quantities
1. The Owner reserves the right to increase or decrease the quantity of material to be
furnished or work to be done under the Contract whenever he deems it advisable or
necessary. Such increase or decrease shall in no way violate or invalidate the Con-
tract.
2. For the unit price items included in the bid, the Contractor will be paid for the actual
amount of the authorized work done or material furnished under each item of the
proposal, at the unit price bid for that item. In case the quantity of any item is
increased, the Contractor shall not be entitled to compensation over and above the
unit bid for each item. In case the quantity is decreased, the Contractor shall have
no claim for damages on account of loss of anticipated profits because of such de-
crease.
3. For the contingency items, the Contractor shall be paid for actual quantities in-
stalled or services provided, on written order of the Engineer.
1.02 MEASUREMENT
A. The quantities for payment under this Contract shall be determined by actual measurement of the
completed items, in place and accepted by the Owner, in accordance with Section D - General
Conditions. A representative of the Contractor shall witness all field measurements.
Route 1 Sewer Replacement
Measurement and Payment
Section No. 01 29 01-2
ATTACHMENT A to Addendum 2
IFB #24-33-SD
1.03 PAYMENT
A. Please see Section D – General Terms and Conditions, Article 10 - Payments and Com-
pletion.
1.04 BID ITEMS
A. Item 1: Mobilization
1. Payment for mobilization shall be made at the lump sum provided in the Schedule
of Values for mobilization, upon completion.
2. No measurement shall be made for this item.
3. Lump sum cost for mobilization shall include such items as bonds, insurance, stake-
out, equipment and labor mobilization, field office, progress photographs, project
sign, permits, shop drawings, Contractor’s test pits, and other incidental items, in-
cluding the safe relocation and protection of personal property located within the
easement required prior to commencement of construction. Mobilization shall not
exceed 5.0 percent of the total price bid. Application for maximum 50 percent pay-
ment of mobilization may be made on the first Request for Payment, maximum 40
percent payment on the second Request for Payment, and 10 percent on the final
Request for Payment.
B. Item 2: Traffic Control
1. Payment for furnishing, installing, operating, maintaining, and removing all tem-
porary traffic control measures shall be made based on the lump sum price provided
in the Schedule of Values.
2. No measurement shall be made for this item. Payment shall not be made until the
traffic control measures are in place.
3. The lump sum price shall include all labor, materials, tools, equipment, and services
for furnishing, installing, operating, maintaining, and removal of the traffic control
measures including all signage, barrels, barricades, and other incidental items re-
quired for its proper operation.
C. Super Silt Fence:
1. Payment for furnishing, installing, maintaining and removing super silt fence shall
be made at the linear feet unit price bid provided in the Schedule of Values, as
directed by the Owner, actually installed, complete in place and removed.
2. Measurement for payment for super silt fence shall be the actual linear feet of silt
fence installed per VESCH Plate 3.05-1. The actual length of fence installed will
be paid at 90 percent (90%) of the unit price provided; the remainder 10 percent
Route 1 Sewer Replacement
Measurement and Payment
Section No. 01 29 01-3