Sealed bids for construction of the St. George Crossing Subdivision Project will be
received until September 17th, 2026 at 3:00 PM at the City of Waynesboro City Hall
at 615 North Liberty Street, Waynesboro, Georgia 30330 at which time and place
they will be publicly opened and read. Any bid received after said time and date will
not be considered by the Owner. No bid may be withdrawn after the closing time for
the receipt of bids for a period of sixty (60) days.
1.2 SCOPE OF WORK
The work shall consist of furnishing all products and equipment and performing all labor
necessary to perform the following:
Project shall consist of water improvements including, but not limited to, approximately
3,680 LF 8” ductile iron watermain, 600 LF of 2” watermain, 11 fire hydrants, 40 shortside
laterals, and 21 longside laterals, and miscellaneous improvements.
Project shall consist of sewer improvements including, but not limited to, approximately 23
EA manhole installations (various depths), 4,133 LF 8” sewer main, 1,830 LF 4” sewer
lateral, 61 EA cleanouts and miscellaneous improvements.
Project shall consist of storm improvements including, but not limited to, 2,395 LF 18” HP
storm pipe, 871 LF 24” HP storm pipe, 248 LF 30” HP storm pipe, H.B. traps, grate inlets,
weir inlets, rip-rap, and miscellaneous improvements.
Project shall consist of miscellaneous improvements including, but not limited to, 4”
concrete sidewalk, 6” concrete, 6” GAB, asphalt paving, 18” curb and gutter, 6” curb,
erosion controls, and grading complete.
Time allotted for completion of work is two hundred forty (240) calendar days. All Work
shall be completed in accordance with the plans and specifications.
/DocumentCenter/View/929/00100-Advertisement-to-Bid_St-George